Johnson & Jennings General Contracting, a San Diego-based contractor, has started work for the build-out of 3,362-square-foot corporate offices for TD Waterhouse, a full-service financial planning institution, at 800 Silverado St. in La Jolla. The work involves demolition of the existing office space, and construction of new offices, break rooms and a conference room. Tenant improvements include custom millwork, and new paint and carpet.

Cost: $130,520.

Project superintendent: Steve Erickson.

Project manager: Carrie Chambers.

Architect/interior designer: TSAO Design Group.

Subcontractors: Spooner's Woodworks, Bergelectric, G-P Acoustics, Comfort Systems, Brady Co., Tierra Glass, and Towne Construction.

- - -

Baja Resort Advisors, LLC, based in La Jolla, has begun construction on Ventana al Mar, a 2,300-unit resort housing development, seven miles north of Ensenada, Baja California, Mexico. The first phase of the master-planned residential resort, which includes 75 beachfront homes and 104 luxury condos, is scheduled to be completed within 24 months. The beachfront homes, which will be priced beginning in the mid-$500,000s, range from 2,200 to 2,600 square feet.
Cost: $6 million.
Interior designer: Karen Collignon.
Marketing and development: Baja Resort Advisors, LLC.
Project oversight: Gabriel V. Robles, managing partner.

- - -

Pacific Building Group of San Diego has completed wall panel erection for the two-story, 69,000-square-foot industrial building in San Bernardino for Pacific Coast Steel.
Cost: $4.8 million.
Architect: Smith Consulting Architects.
Landscape architect: Alhambra Group.
Project oversight: Eric Benson, Pacific Coast Steel president.
Structural engineer: Prime Structural Engineering.
Civil engineer: Partners Planning & Engineering.
Mechanical engineer: DEC Engineers.
Electrical engineer: Kruse & Associates.

- - -

Roel Construction Co. of San Diego has completed the parking lot expansion for the Gemological Institute of America in Carlsbad. The expansion adds 470 parking spaces to GIA's world headquarters, the Robert Mouawad campus.
Cost: unavailable.
Architect: Robert R. Coffee Architects & Associates.
Civil engineer: Richard Moore of MCE Consultants.
Project executive: Wayne Hickey.
Project manager: Rob Netzer.
Project engineer: Jason Albrecht.
Project superintendent: Vic Johnson.
Project coordinator: Carmen Ramirez.
Subcontractors: ABC Construction, San Diego Erosion Control, Hale Engineering, Paul Hanson Equipment, DL Olsen & Associates, Big Trees of California, Rossi Concrete, and Bergelectric.

- - -

Bilbro Construction Co., a San Diego-based general contracting firm, has been awarded a contract to complete phase two renovations to the UCSD Moores Cancer Center on the UC San Diego campus in La Jolla. The work, expected to be finished by late July, includes modifications to the main clinic, pharmacy and infusion center.
Cost: $450,000.
Architect: Zimmer Gunsul Frasca Partnership.